On September, 30th 2010  the construction contract of the health center of western Porvoo was handed over to the pleased Client, municipality of Porvoo two months ahead of schedule. The works were started at site on November 14th 2008 and they were completed on September 30th 2010. The renovation of the health center which was operating during the construction works was executed in two stages. The renovated area includes 5042 m2 and the extension area approximately 502 m2. There were no accidents during the whole project.